I love that the excitement is starting to filter through as the construction gathers pace. These updates are great to see
User avatar
lewis97
Admin
Admin
Posts: 4374
Joined: Thu Nov 08, 2012 6:41 am
Location: Hertfordshire

Theme Park Worldwide have posted a few photos on Facebook showing the additional bents installed today.

Image

Image
User avatar
Spacemonkeys
New Member
New Member
Posts: 3
Joined: Wed Jun 01, 2016 6:55 pm

It's a very gentle crest to the slope. Could be carrying some speed over the top.
User avatar
simononestop
Member
Member
Posts: 197
Joined: Mon Jun 15, 2009 1:20 pm
Location: Hastings

It will depend on the camber around that first corner though.
Last edited by Chris on Tue Jul 11, 2017 2:31 pm, edited 1 time in total.
Reason: Corrected spelling.
User avatar
Chris
Admin
Admin
Posts: 2646
Joined: Sun Mar 16, 2003 8:38 pm
Location: London
Contact:

Interesting to compare this to Lightning Rod's top of lift..

Image
User avatar
PhNx Survivor
Member
Member
Posts: 433
Joined: Sat Nov 17, 2012 11:03 am
Location: - Unknown -

I'm grateful and all for a woodie to finally be at Alton.. but seeing that picture of Lightning Rod does sadden me a little. Couldn't of imagined what sort of RMC woodie would of been in place of SW8.. however I'm sure GCI will have something quite surprising, up their sleeves for SW8.
User avatar
Capt.Barnacles
Member
Member
Posts: 616
Joined: Thu Nov 22, 2012 7:19 pm
Location: Stoke-on-Trent

11th July Update

Was on park today, plenty of work going on around the site. The Steve Foster crane was continuously moving a concrete container back and forth for foundation pouring in the area I assume was where the first drop will be. One more bent has gone up at the top end since TPW's post, and several bents working backwards from the brake run have been put up as well. Nothing's happened on the steel mess that I still think will be rockwork rendered, but someone was stood inside it earlier, though I only saw him climbing down so can't be certain what he was working on up there. On top of that there was a deep-ish trench being dug through the gaps in the foundations for the old flume turnaround, I'm assuming this is for the pathway to the plaza indicated in the midst of the ride, as well as part of the queue line. Over the whole site foundations are quickly being finished and connected up with only a few major areas left to do around the first drop leading towards the theming element.

Image
Image
Image
Image
Image
Image
Image
Image
Image

Seems clear the poor weather isn't putting off the work progress at all! Going up so much faster than expected!
Image
Image
User avatar
jasonped
New Member
New Member
Posts: 2
Joined: Tue Jul 11, 2017 5:49 pm

Hi all, I've been following the forum for the past few weeks as SW8 construction has been developing. I thought I'd finally make an account so I can be a bit more active! 

Anyway, thanks to everyone for the pictures and the constant updates. I do think however it's unlikely we are getting a launched lift. Just looking at the latest photos posted by Capt Barnacles and also from referring to the plans, and the foundations, you can see there is a turn with a very tight radius directly after the lift hill with little to no banking. I think we'll most likely just see a LSM lift hill. Something like Maverick? It could possibly be a bit quicker than your average woodies lift, but nothing crazy. 
User avatar
Dom
Member
Member
Posts: 2464
Joined: Thu Dec 30, 2010 11:00 am
Location: Salisbury, Wiltshire
Contact:

Thank you so much for the update. I think what is great about this coaster's construction is that fact that you are able to see how much they get done on a near daily basis because of how open it is for people to get updates.I say this every time I post in this topic, but my god is it flying up, but then again I haven't really got anything to compare it too as this is the first woodie i've followed being constricted in such detail. Is it normal for a wooden coaster to be constructed this quick or are they actually putting in a lot of effort at AT?
User avatar
Adz
Admin
Admin
Posts: 7038
Joined: Tue Nov 18, 2003 6:37 pm
Location: Yorkshire
Contact:

I do believe the ride is ahead of schedule by a few weeks.

It certainly is going up quickly, though not abnormally quick for a woodie. Most coasters go up very quickly once the foundations are done.

Now this part is done you can begin to get a sense of scale from the ride. I'm definitely looking forward to the drop from there, should be comparable to Th13teens but without the trims!
Image
User avatar
Capt.Barnacles
Member
Member
Posts: 616
Joined: Thu Nov 22, 2012 7:19 pm
Location: Stoke-on-Trent

The sense of scale is very apparent now, I strongly suspect there will be several more bents on the drop done by the end of the week, if not the drop done altogether, as three were finished and stacked up ready at the start of the day, and by the time I left at 3pm, two more were almost ready to go.
Image
Image
User avatar
gddevey1012
New Member
New Member
Posts: 20
Joined: Fri Mar 01, 2013 5:02 pm
Location: Kent

jasonped wrote:Hi all, I've been following the forum for the past few weeks as SW8 construction has been developing. I thought I'd finally make an account so I can be a bit more active! 

Anyway, thanks to everyone for the pictures and the constant updates. I do think however it's unlikely we are getting a launched lift. Just looking at the latest photos posted by Capt Barnacles and also from referring to the plans, and the foundations, you can see there is a turn with a very tight radius directly after the lift hill with little to no banking. I think we'll most likely just see a LSM lift hill. Something like Maverick? It could possibly be a bit quicker than your average woodies lift, but nothing crazy. 
Hi Jason 
I am interested in that theory as you are right about it being a tight turn however i dont think we can judge the banking quite yet as the turn could be banking into the first drop, However looking at the plans that first drop is incased in a sound tunnel this makes me wonder why as if it was travelling at a slower speed i doubt that the sound would have been an issue.  I still think a launch but maybe the launch ends before the crest of the lift hill so it does not carry full speed into that first turn.  
User avatar
lewis97
Admin
Admin
Posts: 4374
Joined: Thu Nov 08, 2012 6:41 am
Location: Hertfordshire

Although the photo is somewhat restrictive in what it shows, it is possible to see that additional bents for the first drop have been put in place.

Image

Source: Instagram
User avatar
cactuselves
New Member
New Member
Posts: 31
Joined: Wed Apr 28, 2004 12:12 am
Location: Leek

Those latest bents look overbanked to me!
User avatar
LaurenceColes
New Member
New Member
Posts: 9
Joined: Tue Mar 12, 2013 3:43 am
Location: Bury St Edmunds

Could this possibly be a launched LIM lift hill with that smoother transition at the top? which then gives the coaster some speed into the first banked turn we can see going up?  :P
User avatar
gddevey1012
New Member
New Member
Posts: 20
Joined: Fri Mar 01, 2013 5:02 pm
Location: Kent

cactuselves wrote:Those latest bents look overbanked to me!
Not sure about Overbanked but certainly there is a good degree of banking on them, i think that with that banking the lift could well be launched to some certain degree.  
User avatar
PhNx Survivor
Member
Member
Posts: 433
Joined: Sat Nov 17, 2012 11:03 am
Location: - Unknown -

They are certainly getting a lot done everyday it appears.. and almost have the first segment done.
Exciting times ahead!
User avatar
LaurenceColes
New Member
New Member
Posts: 9
Joined: Tue Mar 12, 2013 3:43 am
Location: Bury St Edmunds

If not a full launch, maybe we'll get a good kick over the top of the lift hill :D 
User avatar
TheDuke
Member
Member
Posts: 204
Joined: Mon Dec 19, 2016 8:38 pm

I'm all always blown away by the pace they're moving at now and its just getting more excited. I'm really liking the look of that hill. This excitement has me arranging a trip to my local woodie and tayto park (as well as the new flume)
User avatar
cactuselves
New Member
New Member
Posts: 31
Joined: Wed Apr 28, 2004 12:12 am
Location: Leek

gddevey1012 wrote:
cactuselves wrote:Those latest bents look overbanked to me!
Not sure about Overbanked but certainly there is a good degree of banking on them, i think that with that banking the lift could well be launched to some certain degree.  
Ha ha ha - yes not sure why I typed overbanked, now that would be extreme!! Was just getting excited that there would be no reason for banking with a traditional lift hill and the very small elevation change from the top of the crest to the last bent that you can see on that photo!